5227 Board of State and Community Corrections
Infrastructure Overview

The BSCC and the California Department of Corrections and Rehabilitation (CDCR) jointly administer three local public safety facilities financing programs with combined total authorizations of up to $1.5 billion in state lease revenue bond financing appropriated to CDCR to partially finance the design and construction of local adult jails and local youthful offender rehabilitative facilities. The BSCC also administers a separate adult local criminal justice facilities financing program with a total authorization of up to $500 million in state lease revenue bond financing appropriated to BSCC to partially finance the design and construction of adult local criminal justice facilities.


MAJOR PROJECT CHANGES Back to Top
  • The Governor's Budget proposes expenditure of $100 million from the $500 million authorized for the adult local criminal justice facilities financing program (Chapter 42, Statutes of 2012). Conditional awards are expected to be made within this financing program in January 2014. The actual amount of expenditures from this financing program during fiscal year 2014-15 will depend on the specific project schedules for counties that receive those awards.


SUMMARY OF PROJECTS Back to Top
Provides expenditures for each major and minor capital project funded in this state agency's budget for the past, current, and budget years. The project phase and fund classification are also identified. The Standard Footnotes key can be accessed by clicking on any footnote link.


Code State Building Program Expenditures Actual
2012-13*
Estimated
2013-14*
Proposed
2014-15*
61 CAPITAL OUTLAY      
  Major Projects      
61.01 STATEWIDE $-   $-   $100,000  
61.01.001 Statewide: Adult Local Criminal Justice Facilities -   -   100,000 PWCn
  Totals, Major Projects $-   $-   $100,000  
Total Expenditures (All Projects) $-   $-   $100,000  

FUNDING Back to Top
Fund Code Fund Actual
2012-13*
Estimated
2013-14*
Proposed
2014-15*
0668 Public Buildings Construction Fund Subaccount $- $- $100,000
Total Expenditures (All Funds) $- $- $100,000

Refer to the
Infrastructure Detail of Appropriations and Adjustments (pdf * - 2K) document for additional information.